Friday, February 1, 2013

Continued Progress on day 2


Began digging this morning to great Equatorial Kenya weather but mid-morning thunderstorms rolled in and halted the progress. We did get a small break in the rain this afternoon to dig for another meter achieving a depth of 9 meters, after two days.

 

At a depth of 6 meters we encountered a sandy loam soil mixed with the clay … this soil type does not make for the secure walls of the pure red clay. As a result, we will install concrete culverts in a vertical position to secure the walls of the well … and for the safety of the diggers, to prevent wall cave in’s.

Picture: Martin Idewa digs to a depth of 9 meters.