Digging on Kipsongo well # 2 started on schedule (7am) and is progressing well. 1:00 pm - Lunch/water break. Depth is currently around 10ft. (Note: I stepped out of the rotation and let the professionals take over after about 2ft). Three diggers alternate. Progress gets slower as we get deeper - longer to get the dirt out by bucket loads, pulled up to the surface by hand. Goal today is 12- 15ft.
Again, another village spectator event ... children getting into trouble, being late to school, as they watch the progress.
No comments:
Post a Comment